Metro Water Services Omohundro WTP Flood Mitigation Projects Intake #4 Passive Screen And Air Burst System

Nashville, Tennessee

Project Description

This construction project included installation of approximately 372 linear feet of 12-inch ductile iron pipe connecting the existing intake to a new passive intake screen. Reynolds removed the existing intake screen and cleaned the area around and inside the existing Intake No. 4 structure. Commercial divers installed approximately 300 linear feet of pipe along the river bottom. All in-water pipe and intake screen installation was performed from a barge platform using a long-stick excavator and an 80-ton crawler crane.

At A Glance

Contract Amount:
$2,447,123.23

Notice to Proceed:
August 2021

Completion Date:
May 26, 2022

Owner Contact Info:
Metro Government of Nashville and Davidson County

Engineer Contact Info:
Greshem Smith

Get in Touch

If we seem a little unique for a construction company, we’ll take it as a compliment. We’d love to talk about what it be like to work together, the way we both want to.