Tennessee Valley Authority – Raccoon Mountain Main Access Tunnel Remediation

Chattanooga, Tennessee

Project Description

This project involved the remediation of the main access tunnel at TVA’s Raccoon Mountain Pumped-Storage Station. Approximately 3,300 SF of tunnel walls were scaled and stabilized with rock bolts and wire mesh reinforcement. Pan drains were installed in areas experiencing water seepage, followed by the application of a 4- to 6-inch layer of shotcrete to reinforce and protect the tunnel walls.

At A Glance

Contract Amount:
$937,330

Notice to Proceed:
August 2018

Completion Date:
September 2018

Owner:
Tennessee Valley Authority

Engineer:
MESA Associates, Inc.

Get in Touch